Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is | |
A. | 3 months [Correct Answer] |
B. | 6 months [Wrong Answer] |
C. | 12 months [Wrong Answer] |
D. | 24 months [Wrong Answer] |