Conductors for high voltage transmission lines are suspended from towers to | |
A. | increase clearance from ground [Correct Answer] |
B. | reduce clearance from ground [Wrong Answer] |
C. | take care of extension in length during summer [Wrong Answer] |
D. | reduce wind and snow loads [Wrong Answer] |
E. | none of the above [Wrong Answer] |