Earliest finish of an activity is always | |
A. | greater than earliest event time of the following node [Wrong Answer] |
B. | less than earliest event time of the following node [Wrong Answer] |
C. | less than or equal to earliest event time of the following node [Correct Answer] |
D. | greater than or equal to earliest event time of the following node [Wrong Answer] |