In time-cost optimization of a project, crashing is done. | |
A. | on all the activities [Wrong Answer] |
B. | on all the activities lying on the critical path [Wrong Answer] |
C. | only on activities lying on the orginal critical path and having flatter cost slopes [Wrong Answer] |
D. | on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope [Correct Answer] |