Pick up the correct step used for scheduling a project by C.P.M. | |
A. | a project is divided into various activities [Wrong Answer] |
B. | required time for each activity is established [Wrong Answer] |
C. | sequence of various activities is made according to their importance [Wrong Answer] |
D. | network is drawn by connecting the activities and the events [Wrong Answer] |
E. | all of the above. [Correct Answer] |