The expected out turn of cement concrete 1 : 2 : 4 per mason per day is | |
A. | 1.5 m3 [Wrong Answer] |
B. | 2.5 m3 [Wrong Answer] |
C. | 3.5 m3 [Wrong Answer] |
D. | 5.0 m3 [Correct Answer] |