The most reliable method of plotting a theodolite traverse, is. | |
A. | by consecutive co-ordinates of each station [Wrong Answer] |
B. | by independent co-ordinates of each station [Correct Answer] |
C. | by plotting included angles and scaling off each traverse leg [Wrong Answer] |
D. | by the tangent method of plotting. [Wrong Answer] |