Under normal conditions using an ordinary cement, the period of removal of the form work, is :. | |
A. | 7 days for beam soffits [Wrong Answer] |
B. | 14 days for bottom slabs of spans 4.6 m and more [Wrong Answer] |
C. | 21 days for bottom beams over 6 m spans [Wrong Answer] |
D. | all the above. [Correct Answer] |