Crash project duration is obtained by summing the | |
A. | normal durations for all the activities [Wrong Answer] |
B. | crash durations for all activities [Wrong Answer] |
C. | crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities [Wrong Answer] |
D. | crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities. [Correct Answer] |