In resources levelling | |
A. | total duration of project is reduced [Wrong Answer] |
B. | total duration of project is increased [Wrong Answer] |
C. | uniform demand of resources is achieved [Correct Answer] |
D. | cost of project is controlled [Wrong Answer] |