If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be | |
A. | 50% [Wrong Answer] |
B. | less than 50% [Wrong Answer] |
C. | more than 50% [Correct Answer] |
D. | 100% [Wrong Answer] |