Total cost of the project is | |
A. | Direct cost and outage cost of project [Wrong Answer] |
B. | Direct cost and overheads [Wrong Answer] |
C. | Direct cost and indirect cost [Correct Answer] |
D. | None of these [Wrong Answer] |