In PERT analysis the duration of the activities is taken as | |
A. | Optimistic time [Wrong Answer] |
B. | Pessimistic time [Wrong Answer] |
C. | Most likely time [Wrong Answer] |
D. | Expected mean time [Correct Answer] |