If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then | |
A. | expected time of activity A is greater than the expected time of activity B [Wrong Answer] |
B. | expected time of activity B is greater than the expected time of activity A [Wrong Answer] |
C. | expected time of both activities A and B are same [Correct Answer] |
D. | none of the above [Wrong Answer] |