In PERT analysis, the time estimates of activities and probability of their occurrence follow | |
A. | normal distribution curve [Wrong Answer] |
B. | Poisson's distribution curve [Wrong Answer] |
C. | Beta - distribution curve [Correct Answer] |
D. | none of the above [Wrong Answer] |