In the penetration macadam construction, the bitumen is | |
A. | sprayed after the aggregates are spread and compacted [Correct Answer] |
B. | premixed with aggregates and then spread [Wrong Answer] |
C. | sprayed before the aggregates are spread and compacted [Wrong Answer] |
D. | none of the above [Wrong Answer] |