For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is | |
A. | dry rolling, wet rolling, application of screening and application of filler [Wrong Answer] |
B. | dry rolling, application of filler, wet rolling and application of screening [Wrong Answer] |
C. | dry rolling, application of screening, wet rolling and application of filler [Correct Answer] |
D. | dry rolling, application of screening, application of filler and wet rolling [Wrong Answer] |