In CBR test the value of CBR is calculated at | |
A. | 2.5 mm penetration only [Wrong Answer] |
B. | 5.0 mm penetration only [Wrong Answer] |
C. | 7.5 mm penetration only [Wrong Answer] |
D. | both 2.5mm and 5.0 mm penetrations [Correct Answer] |