Pick up the incorrect statement from the following. A critical ratio scheduling | |
A. | establishes the relative priorities among various activities on a common basis [Wrong Answer] |
B. | determines the status of each activity [Wrong Answer] |
C. | adjusts automatically changes in activity progress [Wrong Answer] |
D. | is a dynamic system [Wrong Answer] |
E. | none of the above. [Correct Answer] |