The important iule in making a PERT is | |
A. | an event can't be accomplished until activities leading to it are completed [Wrong Answer] |
B. | no activity from any event can be started from preceding event till it is completed [Wrong Answer] |
C. | length of arrow has nothing to do with time [Wrong Answer] |
D. | every activity must be completed before end point is reached [Wrong Answer] |
E. | all of the above. [Correct Answer] |