Slack of various events on the critical path in PERT/CPM chart | |
A. | increases continuously [Wrong Answer] |
B. | decreases continuously [Wrong Answer] |
C. | remains constant [Correct Answer] |
D. | may increase or decrease depending on various factors [Wrong Answer] |
E. | unpredictable. [Wrong Answer] |