The assumption in PERT is | |
A. | a project will always be behind schedule, if left uncorrected [Wrong Answer] |
B. | cost of project will always be more than the estimated cost, if no timely corrections are taken [Wrong Answer] |
C. | a project can be subdivided into a set of predictable, independent activities [Correct Answer] |
D. | activities are fixed and can't be changed , [Wrong Answer] |
E. | commissioning time can be changed, if activities are behind schedule. [Wrong Answer] |