Activity s,lack or float of any event on a PERT/CPM chart is represented by | |
A. | latest start time of succeeding event -earliest finish time of preceding event activity time [Wrong Answer] |
B. | latest start time of the event - earliest start time of the event [Wrong Answer] |
C. | latest finish time of event - earliest finish time of the event [Wrong Answer] |
D. | anyone of the above [Correct Answer] |
E. | none of the above. [Wrong Answer] |