Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it | |
A. | consumes time, but no resources [Wrong Answer] |
B. | consumes resources but no time [Wrong Answer] |
C. | consumes neither time nor resources [Correct Answer] |
D. | is a dangling event [Wrong Answer] |
E. | consumes both resources and time. [Wrong Answer] |