If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good | |
A. | EF=ES+D [Wrong Answer] |
B. | LS=LF-D [Wrong Answer] |
C. | LF = LS + D [Wrong Answer] |
D. | D = EF-ES [Wrong Answer] |
E. | all of the above. [Correct Answer] |