The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as | |
A. | duration [Wrong Answer] |
B. | total float [Wrong Answer] |
C. | free float [Correct Answer] |
D. | interfering float [Wrong Answer] |
E. | none of the above. [Wrong Answer] |