The critical path of a network represents | |
A. | the minimum time required for completion of project [Correct Answer] |
B. | the maximum time required for completion of project [Wrong Answer] |
C. | maximum cost required for completion of project [Wrong Answer] |
D. | minimum cost required for completion of project [Wrong Answer] |
E. | none of the above. [Wrong Answer] |