Pick up the correct statement from the following | |
A. | the float may be positive, zero or negative [Wrong Answer] |
B. | if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed [Wrong Answer] |
C. | if the float of an activity is negative, delay in its performance is bound to delay the completion of project [Wrong Answer] |
D. | if the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project [Wrong Answer] |
E. | all of the above. [Correct Answer] |