Critical path moves along the activities having total float of | |
A. | positive value [Wrong Answer] |
B. | negative value [Wrong Answer] |
C. | zero value [Correct Answer] |
D. | same value [Wrong Answer] |
E. | none of the above. [Wrong Answer] |