The technique for establishing and maintaining priorities among the various jobs of any project is known as | |
A. | event flow scheduling technique [Wrong Answer] |
B. | critical ratio scheduling [Correct Answer] |
C. | slotting technique for scheduling [Wrong Answer] |
D. | short interval scheduling [Wrong Answer] |
E. | none of the above. [Wrong Answer] |