Critical Path Net Work helps an engineer | |
A. | to concentrate his attention on critical activities [Wrong Answer] |
B. | to divert the resources from non-critical advanced activities to critical activities [Wrong Answer] |
C. | to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project [Wrong Answer] |
D. | all of the above [Correct Answer] |
E. | none of the above. [Wrong Answer] |