In PERT analysis, critical path is obtained by joining events having | |
A. | +ve slack [Wrong Answer] |
B. | -ve slack [Wrong Answer] |
C. | zero slack [Correct Answer] |
D. | dummy activities [Wrong Answer] |
E. | critical activities. [Wrong Answer] |