The first method invented for planning projects was | |
A. | bar chart method [Correct Answer] |
B. | milestone chart [Wrong Answer] |
C. | critical path method (CPM) [Wrong Answer] |
D. | programmer evaluation and review technique (PERT) [Wrong Answer] |
E. | none of the above. [Wrong Answer] |