Total float for any activity is defined as the difference between | |
A. | its latest finish time and earliest start time for its successor activity [Wrong Answer] |
B. | its latest start time and earliest start time [Correct Answer] |
C. | its latest start time and earliest finish time [Wrong Answer] |
D. | its earliest finish time and earliest start time for its successor activity [Wrong Answer] |